颐和园电影未删减完整版在线观看|情人电影完整版未删减下载地址|亚洲第4页|父母爱情未删减完整版在线观看,爱的谎言在线观看完整版高清电影,我们相爱吧电影完整版在线观看,婷婷国产

軟題庫 移動APP 掃碼下載APP 隨時隨地移動學(xué)習(xí) 培訓(xùn)課程
試卷名稱 信息系統(tǒng)項目管理師-pmp練習(xí)題-2
考試中心《信息系統(tǒng)項目管理師-pmp練習(xí)題-2》在線考試
試卷年份2017年下半年
試題題型【單選題】
試題內(nèi)容

The customer responsible for overseeing your project asks you to project a written cost estimate that is 30 percent higher than your estimate of the project’s cost. He explains that the budgeting process requires managers to estimate pessimistically to ensure enough money is allocated for projects. What is the best way to handle this ?
A、Add the 30 percent as a lump sum contingency fund to handle project risks.
B、Add the 30 percent to your cost estimate by spreading it evenly across all project activities.
C、Create one cost baseline for budget allocation and a second one for the actual project management plan.
D、Ask for information on risks that would cause your estimate to below.


相關(guān)試題

推薦文章
合作網(wǎng)站內(nèi)容